Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- not held by REPD
- Status
- Revised
- Operator
- ESOS ENERGY
- County
- Merseyside
- Region
- North West
- Country
- England
- Planning authority
- Knowsley
- Planning reference
- 25/00478/PDS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-08-15: Planning Application Submitted
- 2025-10-08: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19502. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.