Quarry Brae - Solar PV Panels
REPD record 19631. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.66 MW
- Status
- Planning Permission Granted
- Operator
- Scottish Water National Operations Control Centre
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 25/02849/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-08-18: Planning Application Submitted
- 2025-10-17: Planning Permission Granted
- 2028-10-17: Planning Permission Expired