slava.energy: UK renewable energy projects
Tesside GigaPark - Battery Energy Storage System
REPD record 19634. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 1000 MW
- Status
- Planning Permission Granted
- Operator
- NatPower UK (NP SPV 27 Limited)
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Redcar and Cleveland
- Planning reference
- R/2026/0364/CL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-05-18: Planning Application Submitted
- 2026-07-13: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19634. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.