Blenches Mill
REPD record 1969. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.1 MW
- Status
- Operational
- Operator
- NextEnery Solar Fund (NESF)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- W/12/02081/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-11-22: Planning Application Submitted
- 2013-11-28: Planning Permission Granted
- 2014-03-31: Operational