slava.energy: UK renewable energy projects
University Of Huddersfield, Queensgate - Solar Panels
REPD record 19704. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.23 MW
- Status
- Planning Permission Granted
- Operator
- University Of Huddersfield
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Kirklees
- Planning reference
- 2025/62/92486/W
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-09-03: Planning Application Submitted
- 2025-11-03: Planning Permission Granted
- 2028-11-03: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19704. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.