slava.energy: UK renewable energy projects
Bournville Primary School, Selworthy Road - Solar Panels
REPD record 19711. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.32 MW
- Status
- Operational
- Operator
- Solar Options For Schools Limited
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- North Somerset
- Planning reference
- 25/P/1860/SJA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-09-24: Planning Application Submitted
- 2025-12-17: Planning Permission Granted
- 2026-02-01: Under Construction
- 2026-04-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19711. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.