Alcatel, Telegraph House - Solar Panels
REPD record 19713. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.3 MW
- Status
- Planning Permission Refused
- Operator
- Private Developer
- County
- London
- Region
- London
- Country
- England
- Planning authority
- Greenwich
- Planning reference
- 25/3119/PN3
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-09-18: Planning Application Submitted
- 2025-10-30: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19713. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.