Bulls Head Farm North
REPD record 1976. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.7 MW
- Status
- Operational
- Operator
- Anesco
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- S/2013/1642/MAF
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-02-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-04-01: Planning Permission Expired
- 2013-12-12: Planning Application Submitted
- 2014-04-01: Planning Permission Granted
- 2014-07-01: Under Construction
- 2014-10-02: Operational