REPD record 1983. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 40 MW
- Status
- Operational
- Operator
- Equitix
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 14/00949/FULLN
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-01: Planning Application Submitted
- 2014-10-15: Planning Permission Refused
- 2015-06-22: Appeal Lodged
- 2015-12-24: Appeal Granted
- 2015-12-24: Planning Permission Granted
- 2016-01-01: Under Construction
- 2016-03-23: Operational
- 2018-12-24: Planning Permission Expired
Open this area on the map