slava.energy: UK renewable energy projects
The Vale Academy, Atherton Way - Solar Panels
REPD record 19846. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.24 MW
- Status
- Planning Permission Granted
- Operator
- Delta Academies Trust
- County
- Lincolnshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Lincolnshire
- Planning reference
- PA/2025/1268
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-01-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-10-17: Planning Application Submitted
- 2026-01-09: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 19846. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.