slava.energy: UK renewable energy projects
Hadley Solar Farm
REPD record 1990. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.6 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 14/02914/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-07: Planning Application Submitted
- 2014-10-06: Planning Permission Granted
- 2015-09-21: Under Construction
- 2015-12-16: Operational
- 2017-10-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1990. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.