slava.energy: UK renewable energy projects
Holwell Hill
REPD record 2004. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2014/1562/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-01: Planning Application Submitted
- 2015-01-30: Planning Permission Refused
- 2015-04-01: Appeal Lodged
- 2015-08-28: Appeal Granted
- 2015-08-28: Planning Permission Granted
- 2016-02-15: Under Construction
- 2016-05-15: Operational
- 2018-08-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2004. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.