slava.energy: UK renewable energy projects
Mountsorrel Quarry, Quorn - Solar Photovoltaic Panels
REPD record 20081. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Tarmac Trading Limited
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Charnwood
- Planning reference
- 2025/PN/0171/LCC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-09-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-12-01: Planning Application Submitted
- 2026-01-07: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20081. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.