slava.energy: UK renewable energy projects

Tesco Extra, Reigate Road - Solar Panels

REPD record 20101. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
0.38 MW
Status
Planning Permission Granted
Operator
Tesco Plc
County
Surrey
Region
South East
Country
England
Planning authority
Mole Valley
Planning reference
MO/2025/02730
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2026-05-12

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20101. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.