Docks Way Disposal Site, Docks Way - Battery Energy Storage System
REPD record 20120. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 1 MW
- Status
- Planning Permission Granted
- Operator
- Newport City Council
- County
- Gwent
- Region
- Wales
- Country
- Wales
- Planning authority
- Newport
- Planning reference
- 25/0991
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-11-20: Planning Application Submitted
- 2026-02-12: Planning Permission Granted
- 2031-02-12: Planning Permission Expired