Primrose Hill Farm
REPD record 2014. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.7 MW
- Status
- Operational
- Operator
- Sun & Soil
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- East Lindsey
- Planning reference
- S/216/00470/14
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-25: Planning Application Submitted
- 2014-08-09: Planning Permission Granted
- 2015-01-15: Under Construction
- 2015-03-25: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2014. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.