slava.energy: UK renewable energy projects
Loudon Way, Repton Park South - Battery Energy Storage Facility
REPD record 20179. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 0.2 MW
- Status
- Planning Permission Refused
- Operator
- AMP Clean Energy
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Ashford
- Planning reference
- PA/2025/2065
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-12-19: Planning Application Submitted
- 2026-02-13: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20179. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.