slava.energy: UK renewable energy projects
Windmill Lane - Solar Panels
REPD record 20287. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- David Lloyd Leisure Limited
- County
- Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- York
- Planning reference
- 25/02498/SOLAR
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-04-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-01-06: Planning Application Submitted
- 2026-03-03: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20287. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.