slava.energy: UK renewable energy projects
Landmead Farm (East Hanney)
REPD record 2030. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 46 MW
- Status
- Operational
- Operator
- First Solar/Innogy (previously BELECTRIC Solar)/Foresight Solar Fund
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- Vale of White Horse
- Planning reference
- P13/V1664/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-22: Planning Application Submitted
- 2013-10-29: Planning Permission Granted
- 2014-11-07: Under Construction
- 2014-12-19: Operational
- 2022-10-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2030. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.