slava.energy: UK renewable energy projects
Lynt Farm
REPD record 2035. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 27 MW
- Status
- Operational
- Operator
- Meag
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/14/1048
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-04-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-20: Planning Application Submitted
- 2015-01-09: Planning Permission Granted
- 2015-01-15: Under Construction
- 2015-03-31: Operational
- 2018-01-09: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2035. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.