Inkersall Primary Academy, Inkersall Green Road - Solar Panels
REPD record 20431. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.16 MW
- Status
- Planning Permission Granted
- Operator
- Solar Options For Schools Limited
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Chesterfield
- Planning reference
- CHE/26/00087/SOLPAN
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-02-05: Planning Application Submitted
- 2026-03-24: Planning Permission Granted
- 2031-03-24: Planning Permission Expired