slava.energy: UK renewable energy projects
Dubbers China Clay Works, Nanpean - Wind Turbines
REPD record 20515. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- Clean Earth Energy Limited
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA25/09509
- Turbines
- 2
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-02-16: Planning Application Submitted
- 2026-07-15: Planning Permission Granted
- 2029-07-15: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20515. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.