Bartlett Business Park - Solar Panels

REPD record 20596. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
2.08 MW
Status
Planning Permission Granted
Operator
Indurent Management Limited
County
Cambridgeshire
Region
Eastern
Country
England
Planning authority
Fenland
Planning reference
F/YR26/0195/PNSOL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2026-06-09

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map