Sleaford Renewable Energy Plant
REPD record 206. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 40 MW
- Status
- Operational
- Operator
- Glenmont Partners
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Kesteven
- Planning reference
- 08/0844
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-08-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-11-04: Planning Permission Expired
- 2008-08-20: Planning Application Submitted
- 2008-11-04: Planning Permission Granted
- 2012-05-10: Under Construction
- 2014-11-28: Operational