Stowbridge Farm
REPD record 2065. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 24 MW
- Status
- Operational
- Operator
- Magnetar Solar
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- East Cambridgeshire
- Planning reference
- 12/00732/ESF
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-02-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-09-24: Planning Application Submitted
- 2012-12-10: Planning Permission Granted
- 2014-03-28: Operational
- 2014-12-10: Planning Permission Expired
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2065. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.