slava.energy: UK renewable energy projects
Holloway Farm, Great Milton - Solar Arrays
REPD record 20671. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.3 MW
- Status
- Planning Application Submitted
- Operator
- Holloway Farm Industrial Park Limited
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- South Oxfordshire
- Planning reference
- P26/S0932/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-03-24: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 20671. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.