Tower Hill Farm
REPD record 2077. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.1 MW
- Status
- Operational
- Operator
- NextEnergy Solar Fund (NESF)
- County
- Avon
- Region
- South West
- Country
- England
- Planning authority
- South Gloucestershire
- Planning reference
- PT14/2810/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-16: Planning Application Submitted
- 2014-10-15: Planning Permission Granted
- 2015-01-01: Under Construction
- 2015-03-30: Operational
- 2017-10-15: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2077. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.