Water Eaton Farm / Port Farm
REPD record 2085. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 34.8 MW
- Status
- Operational
- Operator
- Foresight& Vogt solar
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 14/04326/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-03-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-04-25: Planning Application Submitted
- 2014-08-21: Planning Permission Granted
- 2014-10-01: Under Construction
- 2015-03-25: Operational
Open this area on the map