slava.energy: UK renewable energy projects
Bommertown Solar Farm
REPD record 2101. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Steadfast Molland Solar Ltd
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- North Devon
- Planning reference
- 54402
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-07-30: Planning Application Submitted
- 2013-10-23: Planning Permission Refused
- 2014-08-05: Appeal Granted
- 2014-08-05: Planning Permission Granted
- 2015-12-16: Operational
- 2016-02-06: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2101. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.