Chapel Banks, Curwen Road - Solar Panels
REPD record 21016. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.2 MW
- Status
- Planning Permission Granted
- Operator
- Murphy Technologies Limited
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- REJ/2026/0002
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-06-02: Planning Application Submitted
- 2026-07-10: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 21016. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.