slava.energy: UK renewable energy projects
Northern Gateway Distribution Centre,Central Road North - Solar Panels
REPD record 21033. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.55 MW
- Status
- Planning Permission Granted
- Operator
- eEnergy Group PLC
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Dartford
- Planning reference
- 26/00651/P14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-06-12: Planning Application Submitted
- 2026-08-05: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 21033. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.