Chapel Lane Parley Solar Farm Phase 2
REPD record 2105. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 36 MW
- Status
- Operational
- Operator
- Eco Sustainable Solutions
- County
- Dorset
- Region
- South West
- Country
- England
- Planning authority
- Bournemouth, Christchurch and Poole
- Planning reference
- 8/13/0332
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-16: Planning Application Submitted
- 2013-09-26: Planning Permission Expired
- 2013-09-26: Planning Permission Granted
- 2014-03-01: Under Construction
- 2014-08-29: Operational