Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 40 MW
- Status
- Planning Application Submitted
- Operator
- S & L Energy Limited
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- High Peak
- Planning reference
- HPK/2026/0188
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2026-06-01: Planning Application Submitted
Open this area on the map