Bystock Solar Farm
REPD record 2112. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.1 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- East Devon
- Planning reference
- 14/1560/MFUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-03: Planning Application Submitted
- 2014-09-30: Planning Permission Granted
- 2015-01-29: Under Construction
- 2015-03-31: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2112. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.