Conesby Solar Farm
REPD record 21246. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 72 MW
- Status
- Under Construction
- Operator
- Rivington Energy
- County
- Lincolnshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Lincolnshire
- Planning reference
- PA/2018/2140
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-11-07: Planning Application Submitted
- 2019-02-01: Planning Permission Granted
- 2025-10-01: Under Construction
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 21246. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.