slava.energy: UK renewable energy projects
Bentley Estate
REPD record 2132. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- East Sussex
- Region
- South East
- Country
- England
- Planning authority
- Wealden
- Planning reference
- WD/2014/1245/MAJ
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-20: Planning Application Submitted
- 2014-08-28: Planning Permission Refused
- 2015-03-23: Appeal Lodged
- 2015-07-23: Appeal Granted
- 2015-07-23: Planning Permission Granted
- 2015-09-23: Under Construction
- 2015-12-17: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2132. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.