Burton Farm
REPD record 2157. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.4 MW
- Status
- Operational
- Operator
- Quercus Renewable Holding 2
- County
- Warwickshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Stratford-on-Avon
- Planning reference
- 14/00536/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-08-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-02-18: Planning Application Submitted
- 2014-07-10: Planning Permission Granted
- 2015-01-28: Under Construction
- 2015-03-15: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2157. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.