Lower End Farm
REPD record 2159. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Operational
- Operator
- Good Energy Generation
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 14/02273/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-08-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-03-12: Planning Application Submitted
- 2014-08-26: Planning Permission Granted
- 2015-05-30: Under Construction
- 2015-06-30: Operational
Open this area on the map