Mount Farm
REPD record 2175. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 22 MW
- Status
- Operational
- Operator
- INRG (Solar Park) 14
- County
- Hereford and Worcester
- Region
- West Midlands
- Country
- England
- Planning authority
- Wychavon
- Planning reference
- 14/01029
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-13: Planning Application Submitted
- 2014-09-15: Planning Permission Refused
- 2015-02-02: Appeal Lodged
- 2015-07-06: Appeal Granted
- 2015-07-06: Planning Permission Granted
- 2016-01-15: Under Construction
- 2016-03-23: Operational
- 2018-07-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2175. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.