Puriton Landfill Solar Farm
REPD record 2190. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 11.4 MW
- Status
- Operational
- Operator
- SBC Renewables
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 42/14/00012
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-02-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-25: Planning Application Submitted
- 2014-09-23: Planning Permission Granted
- 2015-09-23: Planning Permission Expired
- 2015-10-01: Under Construction
- 2015-12-01: Operational
Open this area on the map