slava.energy: UK renewable energy projects
Double H Nurseries Biomass Plant
REPD record 22. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 1.5 MW
- Status
- Operational
- Operator
- Double H Nurseries
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- New Forest
- Planning reference
- 12/98264
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-08-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-01-25: Planning Application Submitted
- 2012-05-29: Planning Permission Granted
- 2012-12-15: Operational
- 2013-05-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 22. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.