Langar Lane
REPD record 2210. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Kappa Solar& OPDE
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Rushcliffe
- Planning reference
- 14/01594/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-12-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-06: Planning Application Submitted
- 2014-12-05: Planning Permission Granted
- 2015-10-05: Under Construction
- 2016-06-15: Operational
- 2017-12-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2210. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.