Askern Colliery solar farm
REPD record 2213. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Anesco
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Doncaster
- Planning reference
- 14/01829/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-11-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-01: Planning Application Submitted
- 2014-12-08: Planning Permission Granted
- 2015-03-12: Under Construction
- 2015-08-14: Operational
- 2017-12-08: Planning Permission Expired