slava.energy: UK renewable energy projects
Hill Farm
REPD record 2223. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 15.9 MW
- Status
- Abandoned
- Operator
- Cookley Solar Park Ltd
- County
- Suffolk
- Region
- Eastern
- Country
- England
- Planning authority
- East Suffolk
- Planning reference
- DC/14/2150/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-02-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-11: Planning Application Submitted
- 2014-11-11: Planning Permission Granted
- 2017-11-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2223. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.