Foel Fawr
REPD record 2235. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.1 MW
- Status
- Planning Permission Expired
- Operator
- Marcol Afan Energy
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Bridgend
- Planning reference
- P/14/543/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-06-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-15: Planning Application Submitted
- 2015-06-12: Planning Permission Refused
- 2015-11-24: Appeal Lodged
- 2016-04-22: Appeal Granted
- 2016-04-22: Planning Permission Granted
- 2021-04-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2235. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.