slava.energy: UK renewable energy projects

Foel Fawr

REPD record 2235. Status: Planning Permission Expired.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
5.1 MW
Status
Planning Permission Expired
Operator
Marcol Afan Energy
County
Mid Glamorgan
Region
Wales
Country
Wales
Planning authority
Bridgend
Planning reference
P/14/543/FUL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2020-06-09

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2235. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.