Ballinderry Road Solar Phase 1 (Lisburn)
REPD record 2236. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 13.5 MW
- Status
- Operational
- Operator
- Hadstone Energy/Island Green Power
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Lisburn and Castlereagh
- Planning reference
- S/2014/0492/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-03-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-22: Planning Application Submitted
- 2014-11-11: Planning Permission Granted
- 2016-06-01: Under Construction
- 2017-02-20: Operational
- 2019-11-11: Planning Permission Expired