slava.energy: UK renewable energy projects
GDL Wymeswold Solar Farm/land off the A6006
REPD record 2237. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6.1 MW
- Status
- Operational
- Operator
- Green Switch Solutions
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Charnwood
- Planning reference
- P/14/1484/2
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-10-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-07: Planning Application Submitted
- 2015-02-11: Planning Permission Granted
- 2015-12-16: Under Construction
- 2016-02-16: Operational
- 2018-02-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2237. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.