slava.energy: UK renewable energy projects
Wilbees Farm
REPD record 2258. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Hive Energy
- County
- East Sussex
- Region
- South East
- Country
- England
- Planning authority
- Wealden
- Planning reference
- WD/2014/1838/MEA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-11-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-05: Planning Application Submitted
- 2014-11-14: Planning Permission Granted
- 2016-07-01: Under Construction
- 2016-10-21: Operational
- 2017-11-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2258. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.