Welbeck Solar / Hazel Gap
REPD record 2260. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 16 MW
- Status
- Operational
- Operator
- Solar century & Magnetar Solar
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Bassetlaw
- Planning reference
- 14/01030/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-08-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-08-14: Planning Application Submitted
- 2015-01-09: Planning Permission Granted
- 2015-01-10: Under Construction
- 2015-03-19: Operational
- 2018-01-09: Planning Permission Expired