Park Farm (Claverdon)
REPD record 2262. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7.5 MW
- Status
- Appeal Refused
- Operator
- BERTY 003
- County
- Warwickshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Stratford-on-Avon
- Planning reference
- 14/02034/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-15: Planning Application Submitted
- 2015-03-12: Planning Permission Refused
- 2015-08-21: Appeal Lodged
- 2016-04-20: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 2262. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.